Welcome Resource Center in Southern California
Case Study

Welcome Resource Center

Civic · Southern California

Caston self-performed eight scopes on the Welcome Resource Center, with metal panels, lath and plaster, and fiber cement panels all provided by Caston rather than the typical three separate contractors, and exterior finishes sourced from three different continents.

3 photos · Click any image to enlarge

Market
Civic
Location
Southern California
Scopes
Eight under one contract
Exterior
Panels, plaster, and fiber cement by Caston
Consolidation
Three contractors' worth of work
Sourcing
Exterior finishes from three continents

Three exterior scopes, one contractor.

The exterior combined metal panels, lath and plaster, and fiber cement panels, scopes that typically go to three separate contractors with three sets of tolerances.

The exterior finishes were sourced from three different continents, so procurement, lead times, and installation sequencing all had to be coordinated tightly.

How Caston Built It

The approach that kept the date

  • Three scopes became one

    Metal panels, lath and plaster, and fiber cement panels were all provided through Caston instead of three separate contractors.

  • Global sourcing, local control

    Exterior finishes sourced from three different continents were tracked and sequenced by the same team installing them.

  • Eight scopes under one contract

    Framing, plaster, panels, scaffolding, sheet metal, rigid insulation, and air barriers moved as one package.

  • One tolerance chain

    Because Caston built the framing, the barriers, and the panels, the exterior tolerances held from structure to finish.

Scope Self-Performed

  • Metal stud framing
  • Lath and plaster
  • Metal panels
  • Fiber cement panels
  • Scaffolding
  • Sheet metal
  • Rigid insulation
  • Air barriers

Outcome

3 to 1

Exterior scopes consolidated with Caston

3

Continents sourced for exterior finishes

8

Scopes self-performed

1

Contractor for panels, plaster, and fiber cement