Pomona College Rains Center in Claremont, CA
Case Study

Pomona College Rains Center

Higher Education · Claremont, CA

Caston self-performed eleven scopes at Pomona College's Rains Center, including GFRG and the glass fiber concrete panels Caston provided for the project.

3 photos · Click any image to enlarge

Market
Higher Education
Location
Claremont, CA
Scopes
Eleven under one contract
Feature
Glass fiber concrete panels
Specialty
GFRG work
Role
Self-performed specialty trades

Eleven scopes, including the glass fiber panels.

The Rains Center package spanned eleven scopes, from framing and fireproofing through GFRG, glass fiber concrete panels, FRP, and air barriers.

The glass fiber concrete panels were a feature of the project, and Caston provided them as part of the same contract that built the walls they attach to.

How Caston Built It

The approach that kept the date

  • The panels came from Caston

    The glass fiber concrete panels were provided by Caston, coordinated with the framing, air barriers, and finishes around them.

  • GFRG in house

    Glass fiber reinforced gypsum work was self-performed alongside the plaster scopes it relates to.

  • Eleven scopes, one contract

    Framing, fireproofing, carpentry, plaster, GFRG, panels, scaffolding, insulation, drywall, air barriers, and FRP all ran through one team.

  • One accountable partner

    The campus dealt with a single contractor across a package that would normally fragment across several.

Scope Self-Performed

  • Metal stud framing
  • Spray applied fireproofing
  • Rough carpentry
  • Lath and plaster
  • GFRG
  • Glass fiber concrete panels
  • Scaffolding
  • Insulation
  • Drywall
  • Air barriers
  • FRP

Outcome

11

Scopes under one Caston contract

Glass fiber

Concrete panels provided by Caston

GFRG

Specialty glass fiber work self-performed

1

Accountable partner across the package