Caston self-performed eleven scopes on Cypress College's Science, Engineering and Math Building, highlighted by ultra-high-performance concrete panels engineered under design-build deferred approval and finished to match the campus's existing exposed aggregate panels.

4 photos · Click any image to enlarge

Market
Higher Education
Location
Cypress, CA
Scopes
Eleven under one contract
Feature
Ultra-high-performance concrete panels
Engineering
Design-build deferred approval
Finish
Custom exposed aggregate match

Panels engineered to match the campus around them.

The building's ultra-high-performance concrete panels required design-build deferred approval engineering and shop drawings before a single panel could be made.

The panels also carried a custom finish that had to match the existing campus panels, including their exposed aggregate, so the new building read as part of the campus.

How Caston Built It

The approach that kept the date

  • Engineered under deferred approval

    Caston ran design-build deferred approval engineering and produced the shop drawings for the UHPC panel system.

  • Custom finish matching

    The panel finish was developed to match the existing campus panels, exposed aggregate included.

  • Eleven scopes, one team

    Framing, fireproofing, carpentry, plaster, acoustical plaster, UHPC panels, scaffolding, sheet metal, drywall, fire protection specialties, and air barriers ran through Caston.

  • Envelope and interior together

    The same team responsible for the panels also built the walls behind them, so tolerances held across the whole assembly.

Scope Self-Performed

  • Metal stud framing
  • Spray applied fireproofing
  • Rough carpentry
  • Lath and plaster
  • Acoustical plaster
  • Ultra-high-performance concrete panels
  • Scaffolding
  • Sheet metal
  • Drywall
  • Fire protection specialties
  • Air barriers

Outcome

UHPC

Panels engineered under design-build deferred approval

Matched

Custom exposed aggregate finish to the existing campus panels

11

Scopes self-performed under one contract

1

Partner for envelope and interior

Have a project with a date that cannot move?